The need
Westgroup needed homes for its employees in Teton Valley, where housing is hard to find.
What we built
Over three phases, 8 single-story Ridgelines and 2 two-story Westleys: 18 units and 30 bedrooms.
The result
The first 8 homes were done before the foundations were ready. Westgroup is now building Phase 4: 2 Ridgelines stacked on top of 2 Dakotas.
Why it worked
“In fact, they had all 8 units completed before we were ready with the foundations onsite.” John Gavin, Westgroup

Why modular

Westgroup needed a place for its team to live in Victor, where housing for workers is hard to come by and so are the trades to build it. Building in our factory meant the homes were coming together in Idaho Falls while the site got ready in Teton Valley.

Growing one phase at a time

Westgroup didn't build it all at once. Phase 1 was four Ridgelines. They came back for two Westleys, then four more Ridgelines. Phase 4 goes up instead of out: 3-bed Ridgelines stacked on top of two-unit Dakotas.

Why we love this one

It shows how the system grows with a business. Start with what you need, add more when you're ready, and stack when land is tight. Every phase, they came back to us.

Plans: Westley, Ridgeline, Dakota

Built for: Workforce housing

Download one-pager (PDF)

Built in phases

  1. Crane setting an upper module at Westgroup employee housing in Victor, Idaho
    Photo: Westgroup, Victor, Idaho (general site photo, not this phase)

    Phase 1

    4 Ridgelines, 2 bed each

    Set
    2024
    Plans
    Ridgeline
    Units
    4
  2. Finished two-story Westley buildings with teal doors at Westgroup employee housing in Victor, Idaho
    Photo: Westgroup Phase 2, Victor, Idaho

    Phase 2

    2 Westleys, 5 units and 7 bedrooms each

    Set
    2024
    Plans
    Westley
    Units
    10
  3. Aerial photo of the two-story buildings at Westgroup employee housing in Victor, Idaho
    Photo: Westgroup, Victor, Idaho (general site photo, not this phase)

    Phase 3

    4 Ridgelines, 2 bed each

    Set
    2024
    Plans
    Ridgeline
    Units
    4
  4. Phase 4 at Westgroup in Victor, Idaho: Ridgelines stacked on Dakota modules, two cranes
    Photo: Westgroup Phase 4, Victor, Idaho

    Phase 4 In progress

    One stacked building: 2 two-unit Dakotas on the main level (4 units, 2 bed each), with 2 three-bed Ridgelines stacked on top. 6 units, 14 bedrooms.

    Plans
    Dakota, Ridgeline
    Units
    6
    Sq ft
    4,238 conditioned (2,119 per level), plus 162 of decks

“We contracted with Mountain Valley Prefab to build (8) 2-bedroom modular units for employee housing in Driggs ID. The quality was top notch. They completed the homes ahead of schedule – which is REALLY uncommon in the construction industry. In fact, they had all 8 units completed before we were ready with the foundations onsite. Their set crew was very professional, and the final product turned out great. They were super easy to work with, from the initial contract, to choosing colors and options to the final completion and occupancy. I would highly recommend them.”

John Gavin, Westgroup
More photos